Conservative Chief Whip Councillor John Goulandris will be revisiting issues arising from the Temple Island redevelopment at the next meeting of Full Council on Tuesday, 8 September.
The move follows the decision taken by the Strategy & Resources Committee in July to approve a variation to an existing agreement with Legal & General, a change which is expected to reduce the amount of affordable housing delivered on the site by around 50%.
Concerns have also been raised that a rent guarantee provided by the Council could increase the level of financial risk borne by local taxpayers over the lifetime of the project.
The changes have prompted wider questions about how the public interest can best be protected when major regeneration agreements are renegotiated in response to changing economic circumstances. The variation to the original agreement has also raised concerns about whether risk and reward are being shared fairly between public and private sector partners.
In response, Cllr Goulandris has tabled the Conservative Group's "silver" motion, which calls for a review of public-private partnership arrangements. The review would examine ways to better protect affordable housing commitments, strengthen financial safeguards for taxpayers, improve transparency and ensure risks are shared more fairly throughout the lifespan of major regeneration schemes.
The Conservative Group recognises that the review would not seek to reopen the Temple Island decision itself but would instead focus on identifying lessons that can strengthen future regeneration partnerships and better protect the interests of Bristol residents.
Cllr Goulandris (Stoke Bishop) said: "When Members considered the variation to the original agreement with Legal & General, it became clear that there were limited mechanisms available to secure some of the commitments that had originally underpinned the project.
"While there were differing views on whether the variation should proceed, the debate highlighted important questions about how public-private partnerships are structured and managed when circumstances change.
"We acknowledge that major regeneration schemes can face significant economic pressures and that agreements may occasionally need to be revisited. However, where public money and public assets are involved, taxpayers must be adequately protected, and affordable housing commitments should not be easily diluted.
"Our proposal is not about re-examining one decision. It is about learning lessons and ensuring future agreements are more robust, more transparent and better balanced between public benefit and private reward.
"If we are serious about restoring public confidence in major development projects, we need stronger safeguards, clearer accountability and a better framework for managing risk."
CONTACT JOHN GOULANDRIS: 07825-315636
Note to Editor:- please find below a copy of the Conservative ‘silver’ motion
BETTER PROTECTION FOR LOCAL TAXPAYERS IN PARTNERSHIP AGREEMENTS
“This Council remains concerned by aspects of the recent decision to vary the partnership arrangements for the redevelopment of the vacant Temple Island site.
The variation was approved only after the use of a casting vote and included significant changes to the original scheme, including a long-term Council commitment associated with office accommodation and a reduction in the proportion of affordable housing to be delivered.
Critics of the decision have questioned whether the revised arrangements expose Bristol taxpayers to excessive financial risk from future office voids or reduced occupancy, whether an appropriate balance of risk exists between public and private sector partners, and whether the market evidence relied upon sufficiently justified the changes. Concerns have also been raised that such variations may set a precedent for future amendments which reduce public benefit.
Regardless of differing views on the merits of the Temple Island development itself, Council recognises the legitimate public interest in ensuring that governance, procurement and development partnership arrangements adequately protect Bristol residents and taxpayers.
Council therefore calls on the Strategy & Resources Committee to establish an inquiry day, cross-party working group, or other appropriate review mechanism to consider:
- How affordable housing commitments can be better protected throughout the lifecycle of major development schemes.
- How financial risks associated with commercial office accommodation can be more effectively managed and shared.
- Whether Members receive sufficient information and transparency to assess market evidence, viability assessments, and the nature of contractual and non-contractual obligations within development agreements.
- Under what circumstances material variations to major development agreements should be considered acceptable.
- The strengths, weaknesses and opportunities for reform of current development partnership and procurement models.
- How public confidence can be strengthened and Bristol taxpayers better protected when significant public funds and assets are involved.
- What lessons can be learned from the Temple Island experience and how those lessons should inform future decision-making.
Council further requests that the review report back to Full Council, with recommendations for improving governance, accountability, transparency and value-for-money safeguards in future major regeneration projects.”